JamR
Moderator
Bridge at the Luge - The additional planking to extend the new bridge to a total length of 12' is all prepped for installation.
Should be an easy install and should take less than an hour. New planking is pre-drilled and countersunk, and set up with wheels and handles to roll it to the site. All we need to do is drive-in 33 lag screws and were done. I have 4 ratchets ready to go.
I'll be at the Cooks parking lot between 7:30 and 7:45 tomorrow morning and would like to get started by 8:00. I'd like to finish the bridge and start riding by 9:15 to Old Camp.
If you would like to help out and ride in the morning, e-mail me; post here; or just show up at Cooks in the morning.
I'll be the one with a 12' bridge in a 6' truck bed
See ya tomorrow.
\
/
Should be an easy install and should take less than an hour. New planking is pre-drilled and countersunk, and set up with wheels and handles to roll it to the site. All we need to do is drive-in 33 lag screws and were done. I have 4 ratchets ready to go.
I'll be at the Cooks parking lot between 7:30 and 7:45 tomorrow morning and would like to get started by 8:00. I'd like to finish the bridge and start riding by 9:15 to Old Camp.
If you would like to help out and ride in the morning, e-mail me; post here; or just show up at Cooks in the morning.
I'll be the one with a 12' bridge in a 6' truck bed
See ya tomorrow.
\